Calendar starting on the 1st with partial weeks

My team is working on some allocation numbers and I haven't been able to figure out how this calendar build should work.  Each month/week grouping should start on the 1st of the month and count in 7 day (or less) increments until the end of each month.  With this information, I will be able to allocate how many people need to be available per week and per month without having to worry about roll-overs between months.

Week Groupings:

Jul 1-7Jul 8-14Jul 15-21Jul 22-28Jul 29-31
Aug 1-7Aug 8-14Aug 15-21Aug 22-28Aug 29-31
Sept 1-7Sept 8-14Sept 15-21Sept 22-28Sept 29-30
Oct 1-7Oct 8-14Oct 15-21Oct 22-28Oct 29-31

I just can't figure out how to do the extra group of leftover days.  Would it be a good place to start to group the day numbers to assign MonthName, Week1, Week2, Week3, Week4, Week5?

Thank you

1 Solution

Accepted Solutions
qliksus
Valued Contributor

Re: Calendar starting on the 1st with partial weeks

As you want to group within the month without crossover the below logic should work

LOAD Date, month(Date), ceil(day(Date)/7) as week

From table ;

2 Replies
qliksus
Valued Contributor

Re: Calendar starting on the 1st with partial weeks

As you want to group within the month without crossover the below logic should work

LOAD Date, month(Date), ceil(day(Date)/7) as week

From table ;

iamscribe
New Contributor III

Re: Calendar starting on the 1st with partial weeks

Thank you Susant,

This worked for me:

ceil(Day(Date(D))/7 as WeekNum