Not applicable

NetWorkDays Function to include Saturday

Hi all

The NetWorkDays function in QlikView only considers Monday to Friday when calculating the difference between two dates.

I have been asked to include Saturday as a working day.

I calculate the lead time for an activity in the script of my QlikView report (see below) so that I can then use Median(LeadTime) in the Pivot Table in my report.

NetWorkDays(%_CreatedOn, %_ScheduledOn)-1 as LeadTime

Has anyone included Saturdays in a similar calculation?  How did you do it?

I have a calendar dimension that has a DayCount field (Monday to Friday is 1, Saturday and Sunday are 0).

1 Reply
Not applicable

Re: NetWorkDays Function to include Saturday

Heres a thread that may be of help to you

Network days with working saturday and holidays