Network days function

Good day

Please assist with a network days function that will exclude weekends
and round off the days to 2 decimal places.

Eg. 6 hours = 0.25 days  or

36 hours = 1.50 days or

1 day 18 hours = 1.75 days

This is for Turn Around Time (TAT) calculations.

Regards

Charles

Tags (1)
1 Reply
MVP
MVP

Re: Network days function

Please try to avoid posting the same topic to multiple places.

You've already received some answers here:

Networks days function