Week Logic Requirement..............???

Dear All
I need to Categorize the Weeks for every month as Week1, Wee2,.........
 
If I use this:
'Week'&Ceil(Day(New_Date)/7) as  Weeks
than i am getting the Weeks as Week1, Week2,......
but the problem with this is it is calculating the Weeks as Week1 =  1-7, Week2 = 8-14..................
I don't want this.
I want to calculate Weeks as: Suppose take a example for January 2015 than:
Week1 = Thu, Fri, Sat, Sun (1,2,3,4)
Week1 = Mon, Tues, Wed, Thu, Fri, Sat, Sun (5,6,7,8,9,10,11)............................
Please find the enclosed Sample File for reference.
Regards
Av7eN
2 Replies
aveeeeeee7en
Specialist III
Specialist III
Author

Any Suggestion??

anbu1984
Master III
Master III

Src:

LOAD Required???,

     WeekDay,

     SampleDate,

     WeekNumber,    

     Week(SampleDate) As WeekNo

FROM

[Sample File.xlsx]

(ooxml, embedded labels, table is Sheet1);

Join(Src)

Load WeekNo,'Week'&AutoNumber(RecNo(),Mth) As Weeks ;

Load WeekNo,Max(Month(SampleDate)) as Mth Resident Src Group by WeekNo Order by WeekNo asc;