HI 

Can someone please help me with below requirement Logic and function to be used.

I need to filter by JOB and Task with start and end time for JO  and event respectively.

Log Table:

datetimeEvent
15-07-20191.00 AmJob Start:Turning
15-07-20192.00 AmTask Start: Turning Componrnt 1 load tool
15-07-20192.30 Amtool loaded
15-07-20192.40 AmMachining
15-07-20193.00 AmTask End: Turning Componrnt 1 load tool
15-07-20193.30 AmTask Start: Turning Componrnt 2 load tool
15-07-20194.00 Amtool loaded
15-07-20195.00 AmMachining
15-07-20195.15 AmTask End:Turning Componrnt 2 load tool
15-07-20195.55 AmJob End: Turning
15-07-20196.12 AmJob Start:Milling
15-07-20196.30 AmTask Start: Milling Componrnt 1 load tool
15-07-20197.00 Amtool loaded
15-07-20197.20 AmMachining
15-07-20197.25 AmTask End:Milling Componrnt 1 load tool
15-07-20197.40 AmTask Start: Milling Componrnt 2 load tool
15-07-20197.50 Amtool loaded
15-07-20198.05 AmMachining
15-07-20198.15 AmTask End: Milling Componrnt 2 load tool
15-07-20198.18 AmJob End: Milling
15-07-20198.30 AmJob Start :Cleaning
15-07-20198.35 AMTask Start: CleaningComponrnt 2 load tool
15-07-20198.40 Amtool loaded
15-07-20198.45 AmCleaning
15-07-20198.45 AmTask End: CleaningComponrnt 2 load tool
15-07-20198.45 AmJob End:Cleaning

 

I need to get table similar so that i can filter in the front end by Job and Task

datetimeEventJOBStart TimeEnd Time
15-07-20191.00 AmJob Start:TurningTurning1.00 Am5.55 Am
15-07-20192.00 AmTask Start: Turning Componrnt 1 load toolTurning1.00 Am5.55 Am
15-07-20192.30 Amtool loadedTurning1.00 Am5.55 Am
15-07-20192.40 AmMachiningTurning1.00 Am5.55 Am
15-07-20193.00 AmTask End: Turning Componrnt 1 load toolTurning1.00 Am5.55 Am
15-07-20193.30 AmTask Start: Turning Componrnt 2 load toolTurning1.00 Am5.55 Am
15-07-20194.00 Amtool loadedTurning1.00 Am5.55 Am
15-07-20195.00 AmMachiningTurning1.00 Am5.55 Am
15-07-20195.15 AmTask End:Turning Componrnt 2 load toolTurning1.00 Am5.55 Am
15-07-20195.55 AmJob End: TurningTurning1.00 Am5.55 Am
15-07-20196.12 AmJob Start:MillingMilling6.12 Am8.18 Am
15-07-20196.30 AmTask Start: Milling Componrnt 1 load toolMilling6.12 Am8.18 Am
15-07-20197.00 Amtool loadedMilling6.12 Am8.18 Am
15-07-20197.20 AmMachiningMilling6.12 Am8.18 Am
15-07-20197.25 AmTask End:Milling Componrnt 1 load toolMilling6.12 Am8.18 Am
15-07-20197.40 AmTask Start: Milling Componrnt 2 load toolMilling6.12 Am8.18 Am
15-07-20197.50 Amtool loadedMilling6.12 Am8.18 Am
15-07-20198.05 AmMachiningMilling6.12 Am8.18 Am
15-07-20198.15 AmTask End: Milling Component 2 load toolMilling6.12 Am8.18 Am
15-07-20198.18 AmJob End: MillingMilling6.12 Am8.18 Am
15-07-20198.30 AmJob Start :CleaningCleaning8.30 Am8.45 Am
15-07-20198.35 AMTask Start: CleaningComponrnt 2 load toolCleaning8.30 Am8.45 Am
15-07-20198.40 Amtool loadedCleaning8.30 Am8.45 Am
15-07-20198.45 AmCleaningCleaning8.30 Am8.45 Am
15-07-20198.45 AmTask End: CleaningComponrnt 2 load toolCleaning8.30 Am8.45 Am
15-07-20198.45 AmJob End:CleaningCleaning8.30 Am8.45 Am
1 Solution

Accepted Solutions
MVP
MVP

Re: start and end time with hirarchy

[ NOTE: to show any contributor that you like and appreciate their answers please CLICK the like icon (thumbs up) ]

Here's a way to do it:

Merknad 2019-07-19 173209.png

2 Replies
MVP
MVP

Re: start and end time with hirarchy

[ NOTE: to show any contributor that you like and appreciate their answers please CLICK the like icon (thumbs up) ]

Here's a way to do it:

Merknad 2019-07-19 173209.png

vpanchuda
New Contributor

Re: start and end time with hirarchy

Thanks a lot Petter, Worked well