Display data relevant to previous date from selected date

Hi 

There are so many answers that seem to answer my question - but none of them work for me.....

I want to display a moving average relevant to the previous date (day before) of the selected field.

 

My moving average formula is      RangeAvg(above (count ([Error Code]),0,7))

My date field is called [Created Date]

When the selected created date is e.g. 21/04/2020 - I want the moving average calculation be relevant to 20/04/2020 and the 7 days prior (according the moving average formula).

 

I tried RangeAvg(above (count ({< [Created Date] = {Date(max([Created Date])-1)}>} [Error Code ]),0,7))

but it brings back an error message

 

Appreciate all assistance!!

Michal

Labels (1)
2 Solutions

Accepted Solutions
lironbaram
Partner - Master III
Partner - Master III

HI 

this expression will work in a table with the Date as dimension 

if(sum(Value)>0, RangeSum(Above( ( sum({<Date={">=$(=Date(max(Date)-7))"}>}Value) ) , 1, 7)))

View solution in original post

MichalSa
Contributor II
Contributor II
Author

Thanks!

Can you please explain the difference between :

RangeSum(Above( ( sum({<Date={">=$(=Date(max(Date)-7))"}>}Value) ) , 1, 7)))

and

RangeSum(Above( ( sum({<Date={">=$(=Date(max(Date)-7))"}>}Value) ) , 0, 7)))

View solution in original post

3 Replies
lironbaram
Partner - Master III
Partner - Master III

HI 

this expression will work in a table with the Date as dimension 

if(sum(Value)>0, RangeSum(Above( ( sum({<Date={">=$(=Date(max(Date)-7))"}>}Value) ) , 1, 7)))

MichalSa
Contributor II
Contributor II
Author

Thanks!

Can you please explain the difference between :

RangeSum(Above( ( sum({<Date={">=$(=Date(max(Date)-7))"}>}Value) ) , 1, 7)))

and

RangeSum(Above( ( sum({<Date={">=$(=Date(max(Date)-7))"}>}Value) ) , 0, 7)))

MichalSa
Contributor II
Contributor II
Author

Appreciate the assistance here as well: 

 

Can you please explain the difference between :

RangeSum(Above( ( sum({<Date={">=$(=Date(max(Date)-7))"}>}Value) ) , 1, 7)))

and

RangeSum(Above( ( sum({<Date={">=$(=Date(max(Date)-7))"}>}Value) ) , 0, 7)))