    Need help with Timeline/Gantt Charts expressions

      Hey all,

       

      I am currently creating a Gantt chart to display multiple Stage gates (G0,G1,G2,G3,G4,Finish). I essentially am trying to make a separate bar chart for each stage. These fields (G0,G1,G2,G3,G4,Finish) each contain a date in the MM,DD,YYYY format. I am trying to accomplish this by using this expression and manipulating it according to which stage gate I am representing:

       

      date(num(G1)-num(G0))

       

      What is wierd is that the above expression works exactly as I want it to in the first bar chart to display a bar between these two dates (I added a reference line in Red for the start and end dates as well. My static min is date(YearStart(G0)) and static max is date(YearEnd(G1)). However, when I use the same expression on the other gates ie. (date(num(G2)-num(G1))), it is not displaying the correct bar. Here are some pics for your reference:

       

      Gantts.PNG

       

      Exps.PNG

       

      Any ideas what is going wrong? All properties and other settings are identical between all the graphs other than the expression and axes being changed to the appropriate stage gate fields.

       

      Thanks in advance!

       