      Hi

       

      I have several reload tasks as follows:

       

      Extraction task

       

      Transformation Task 11

      Transformation Task 12

      Transformation Task 13

       

      Transformation Task 2

       

      I would like to achieve the following:

       

      1. Run "Extraction Task".

      2. Run "Transformation Task 11", "Transformation Task 12", "Transformation Task 13" in paralel after "Extraction Task" is completed.

      3. Run "Transformation Task 2" after all "Transformation Task 11", "Transformation Task 12", "Transformation Task 13" are completed.

       

      Is it possible to do with QMC? If not what flow package would you suggest?

       

      Thanks

       

      Darius