5 Replies Latest reply: Jul 22, 2015 8:10 AM by arjun rao RSS

    One of the task stopped to run at scheduled time.

    haimanta Barkakati

      Hi All,

       

      One of the scheduled tasks suddenly stopped to run in our qmc at the scheduled time and now we had to manually execute it on daily basis.

      All the other tasks and services are up and running.

      What can be the probable reason for this ?

       

      There is no log as the task does not run as scheduled, we need to click on the jobs in qmc manually to start the jobs. After we click the logs do get created.

       

       

       

      Once we recreated the entire task again, then the trigger started happening as per schedule

       

       

       

      Version is 11.2. Ram is 256 GB

       

      Expert suggestions required. What could be the exact reason for not getting triggered?