    QVS 9 Scheduled reload failed, normal QV Developer reload ok

      Hi,

      I'm working with QV Server 9 SBE and am trying to schedule reload of a QV document.
      The document reloads fine using Developer on the server, but the scheduled reload in QMC fails.

      I tried to enable log in the qvw file, but no log appears. It seems like the file was not loaded.

      The error message seen in the Status page of QMC says:

      The Source Document was NOT reloaded successfully. DocumentPath=D:\QlikView Storage\Private Data\Source Documents\Test Results.qvw.
      Reload failed.
      The task "ITS/Test Results.qvw" failed. ErrorCount=2