Hi Everyone,

I am currently struggeling with the FirstWorkDate Function.

I am Using

FirstWorkDate(last_data,5,vPublicHolidays)

where last_data is 06.05.2018.

in vPublicHolidays the 01.05.2018 is contained (and it does work in NetWorkDays just fine, I checked that).

The function returns 30.04.2018 but it should be the 27.04.2018, right? (04.05, 03.05, 02.05, 30.04. 27.04.)

Also I had lasta_data as 07.05.2018 and it returned 01.05.2018 which is a specified holiday...

When i am not using the varaible "vPublicHolidays" and only specify 1.5. with makedate it works. But as I said May has 19 Workdays according Net Workdays which uses vPublicHolidays.... (which is correct)

Does anyone know, whats happening there?

Best Regards

Max

1 Solution

Accepted Solutions
max_potass
Creator
Creator
Author

Ok, I found it myself.

I have to put $(vPublicHolidays)

Can someone explain why this is necessary?

View solution in original post

3 Replies
tresesco
MVP
MVP

I am getting 27.04.2018. Could it be a formatting issue? Please check and ensure all dates you are using are in same format.

max_potass
Creator
Creator
Author

Ok, I found it myself.

I have to put $(vPublicHolidays)

Can someone explain why this is necessary?

tresesco
MVP
MVP

That is probably because, your variable has got a definition and not the date values directly entered, and if that is true, it would require to be expanded (using dollar sign) to get the value in it.