Abort Job if condition isn't true (QV 8.5)

Hello,

hope anybody can help me?!

My problem: I want to distribute an QVW-Application only if the data is up to date

At the moment, I have three tasks in one Job (2 reload tasks and 1 distribution task).

- The first checks data (up to date?)

- The second reload the TEST.qvw - application

- The third distribute the TEST.qvw

How can I realize that the document only distribute on actually data?

In QV 9 it can be realized by trigger…but in 8.5?

Thanks, for your answers! [;)]

2 Replies
Not applicable

In 8.5 you have dependencies functionality, regards.

aerfurt85
Contributor
Contributor
Author

Really?

Where can I find them?

...

Moreover,

it's possibility to switch a job (enable / disable) by EDX or by script (macro)?

Thanks!