Unlock a world of possibilities! Login now and discover the exclusive benefits awaiting you.
Good Morning,
as stated in subject, I have some daily reload processes that were scheduled during last months. On last weekend, here has started the Daylight Saving Time period and all scheduled processes are now starting one hour later than before.
The strange thing is that, opening schedule properties form, the time of schedule is correct but planning isn't.
Let's see an example. Considering the highlighted process:
If you open its properties form, it has one daily trigger schedule. Double click on it:
Even if you try to change start time and save, schedule shift remains. E.g.: if you set the above one to 10:15, after saving it you see this:
The only way you have is to delete and re-create the trigger.
Ciao.
Paolo.
Hello Paolo - this sounds like a bug, the best thing to do here is log a ticket with support, being you are a paid Qlik customer licensed with Qlik Sense Server.
Please mark the appropriate replies as CORRECT / HELPFUL so our team and other members know that your question(s) has been answered to your satisfaction.
Regards,
Mike Tarallo
Qlik
What is your system time stamp?
Good Morning,
it's correctly set up on local timezone.
I've got the same problem.
As of now I've only got a few tasks, but this will grow.
I don't have to recreate the trigger. Changing the start date to a date afther the DST got active get the correct scheduling time. But his means that I'll have to do the same when the DST changes again.
Hope this is not "as designed"
Hello Paolo - this sounds like a bug, the best thing to do here is log a ticket with support, being you are a paid Qlik customer licensed with Qlik Sense Server.
Please mark the appropriate replies as CORRECT / HELPFUL so our team and other members know that your question(s) has been answered to your satisfaction.
Regards,
Mike Tarallo
Qlik
Ciao Michael,
I'll ask our Qlik partner to do it.
Thank you.
Hi Peter,
this doesn't happened to me, as you can see in screenshots.
Dear Michael and Paolo.
Please do it.
I reported similar bug (from our customer) to R&D a day ago.
R&D is working on it.
Reagrds,
Hi Paolo,
If you change the startdate 2016-02-16 in today, does this not correct your schedule time?
Seems like a bug. But if they are working on it I supose it will be solved.
Peter.
Hi Peter,
I didn't try changing the date, just time. Now it's too late since I've changed all tasks...
As you can see in this thread, Michael (from Qlik) is following the issue and I've opened a ticket to them last week.
Regards,
Paolo.