Do not input private or sensitive data. View Qlik Privacy & Cookie Policy.
Skip to main content

Announcements
Talend Cloud AWS EU Scheduled Outage: Starting Tues 26 May 21:00 CEST with expected completion Wed 27 May 01:00 CEST
cancel
Showing results for 
Search instead for 
Did you mean: 
DBS1
Contributor III
Contributor III

Making the TMC Plan to success when handler task is successful

Hi Team

I have created two tasks in Talend Management Console and have created a plan out of these two tasks. I have just one step in the plan, one of the task is the main step and the other task act as handler.
I have a requirement that the Plan should go to success state if either the main task or handler task is success. But what I could observe is that when main task is in failed status and handler task is in success status, the entire plan goes to Failed status.

Please help on how to make the Plan goes to success state when either the main task or handler taks is successful.

Labels (5)
1 Reply
Shicong_Hong
Employee
Employee

Hello 

Handlers are designed to only run when a step fails, so it is not possible to leave the plan in a successful state if the handler is triggered to run.

Shicong_Hong_1-1718282490860.png

 

Regards

Shicong