Task is not waiting for the first triggered task to end in TMC Talend

I have scheduled a Job in Talend Management Console (TMC) to run every 5 minutes.

I have also deselected the option of allow parallel run of this task.

Now my job is taking more than 5 minutes to run, but in TMC this job is starting again after 5 minutes instead of waiting for this task to end .

In TAC , when we schedule job to run every 5 minutes, it waits for the task to end before starting the next trigger if the job is taking longer. How can I achieve this in TMC.

Labels (4)
1 Solution

Accepted Solutions
Anonymous
Not applicable

Hi

In TMC, the task will start every 5 minutes and fails with error message "It's not allowed to run this task in parallel" if the 'allow parallel run of this task' option is unchecked, it will not wait for the end of last execution.

 

Regards

Shong

 

View solution in original post

1 Reply
Anonymous
Not applicable

Hi

In TMC, the task will start every 5 minutes and fails with error message "It's not allowed to run this task in parallel" if the 'allow parallel run of this task' option is unchecked, it will not wait for the end of last execution.

 

Regards

Shong