Skip to main content
Announcements
Qlik Connect 2024! Seize endless possibilities! LEARN MORE
cancel
Showing results for 
Search instead for 
Did you mean: 
Vaku1606
Contributor III
Contributor III

Sum IF

Hello,

I have following table:

PLANNED_END_DATE QUANTITY ITEM CALCULATED_DELIVERY_DATE
12/12/2022 6:30 550000 483174 12/31/2022 0:00
11/22/2022 10:50 550000 483174 11/30/2022 0:00
10/31/2022 21:35 201000 483174 10/31/2022 0:00
8/25/2022 22:44 95648 483172 8/31/2022 0:00
10/5/2022 17:42 1000000 483172 9/30/2022 0:00
11/17/2022 18:37 1000000 483172 11/30/2022 0:00
10/24/2022 8:12 369600 483207 9/30/2022 0:00
10/25/2022 18:27 169600 483207 10/31/2022 0:00
11/29/2022 13:56 300000 483207 11/30/2022 0:00
12/7/2022 11:19 400000 483207 12/31/2022 0:00
10/30/2022 0:53 260000 483241 10/31/2022 0:00

 

I would like to have 3 columns in my application according to following rules:

If planned end date > calculated delivery date then Sum the Quantity and show it as  "late orders"

If planned end date = calculated delivery date then Sum the Quantity and show it as  "on time orders"

If planned end date < calculated delivery date then Sum the Quantity and show it as "in advance"

Could you please help?

thanks in advance and regards

Labels (4)
1 Solution

Accepted Solutions
BrunPierre
Partner - Master
Partner - Master

I'd do something like the below

peter_brown_2-1660174297854.png

LOAD DATE(FLOOR(PLANNED_END_DATE)) AS PLANNED_END_DATE,
QUANTITY,
ITEM,
DATE(FLOOR(CALCULATED_DELIVERY_DATE)) AS CALCULATED_DELIVERY_DATE,
IF(DATE(FLOOR(PLANNED_END_DATE)) > DATE(FLOOR(CALCULATED_DELIVERY_DATE)),QUANTITY,
IF(DATE(FLOOR(PLANNED_END_DATE)) = DATE(FLOOR(CALCULATED_DELIVERY_DATE)),QUANTITY,
IF(DATE(FLOOR(PLANNED_END_DATE)) < DATE(FLOOR(CALCULATED_DELIVERY_DATE)),QUANTITY))) AS [NEW QUANTITY],
IF(DATE(FLOOR(PLANNED_END_DATE)) > DATE(FLOOR(CALCULATED_DELIVERY_DATE)),'LATE ORDERS',
IF(DATE(FLOOR(PLANNED_END_DATE)) = DATE(FLOOR(CALCULATED_DELIVERY_DATE)),'ON TIME ORDERS',
IF(DATE(FLOOR(PLANNED_END_DATE)) < DATE(FLOOR(CALCULATED_DELIVERY_DATE)),'IN ADVANCE'))) AS [ORDER STAUS]

FROM TABLE;

 

 

 

 

View solution in original post

2 Replies
BrunPierre
Partner - Master
Partner - Master

I'd do something like the below

peter_brown_2-1660174297854.png

LOAD DATE(FLOOR(PLANNED_END_DATE)) AS PLANNED_END_DATE,
QUANTITY,
ITEM,
DATE(FLOOR(CALCULATED_DELIVERY_DATE)) AS CALCULATED_DELIVERY_DATE,
IF(DATE(FLOOR(PLANNED_END_DATE)) > DATE(FLOOR(CALCULATED_DELIVERY_DATE)),QUANTITY,
IF(DATE(FLOOR(PLANNED_END_DATE)) = DATE(FLOOR(CALCULATED_DELIVERY_DATE)),QUANTITY,
IF(DATE(FLOOR(PLANNED_END_DATE)) < DATE(FLOOR(CALCULATED_DELIVERY_DATE)),QUANTITY))) AS [NEW QUANTITY],
IF(DATE(FLOOR(PLANNED_END_DATE)) > DATE(FLOOR(CALCULATED_DELIVERY_DATE)),'LATE ORDERS',
IF(DATE(FLOOR(PLANNED_END_DATE)) = DATE(FLOOR(CALCULATED_DELIVERY_DATE)),'ON TIME ORDERS',
IF(DATE(FLOOR(PLANNED_END_DATE)) < DATE(FLOOR(CALCULATED_DELIVERY_DATE)),'IN ADVANCE'))) AS [ORDER STAUS]

FROM TABLE;

 

 

 

 

Vaku1606
Contributor III
Contributor III
Author

Works perfectly. Thanks a lot