Automating project documentation generation.

Is there a way to generate project documentation other than via the project menu?  We would like to automatically generate new documentation when we deploy to production maybe using a rest call or via the composecli.

Labels (3)
1 Solution

Accepted Solutions
Nanda_Ravindra
Support
Support

@dpurdy66  You can use the composcli to generate the project document. 

composecli Generate_project --project YOUR_PROJECT_NAME

For other available commands for generate_project you can run the below command:

composecli Generate_project --help

Thanks,

Nanda

View solution in original post

2 Replies
Nanda_Ravindra
Support
Support

@dpurdy66  You can use the composcli to generate the project document. 

composecli Generate_project --project YOUR_PROJECT_NAME

For other available commands for generate_project you can run the below command:

composecli Generate_project --help

Thanks,

Nanda

dpurdy66
Contributor III
Contributor III
Author

The product help does not mention generating the project documentation.  Also, I only want to generate the project documentation HTML file - not do all the stuff mentioned below.

ComposeCli.exe generate_project --project MyProject --stopIfDatamartsNeedRecreation

When the command is run, Compose will:

  • Validate the model.
  • Create any data warehouse tables that do not exist.
  • Validate the data warehouse.
  • Adjust the data warehouse if needed.

    If an Adjust script is needed and --database_already_adjusted is included in the command, the script (DDL) will not be run as it is assumed that the user ran it manually.

  • Generate all data warehouse tasks.

    If Compose encounters an error while generating a data warehouse task, it will skip the problematic task and continue with the remaining tasks.

  • Create, adjust and generate all data marts.

    If the "Adjust" cannot be performed automatically and --stopIfDatamartsNeedRecreation is included in the command, the process will stop.