My first task is running without any issues . Second task is scheduled up on succesful run of first task. But unfortunately the second task is not running. Please let me know if there is a way to fix this issue. Please see the attached screen shot. Thanks for your help in advance. I checked the log file of the first task it is running successfully without any issues.
u are not scheduled ur second job properly,if u successfully scheduled ur 2nd job it won't show "NOT SCHEDULED" on status of ur 2nd job,it should show on succeeded of first job name.
Hi
What Shiva said is absolutely Right.
If you Schedule your second Task Properly depending upon first Task
than it will display below message:
"When Your_Application_Name.qvw has succeeded"
Just to check whether there is problem with Code or Syntax in Second Task (QVW):
Reload the Second task Manually which is Failing.
If the Second Task (QVW) runs Manually without any Error, than first check the Logs which will show
you the reasons for its Failure.
Finally, in your Mounted Folder (Publish Folder), First Copy the Second Task (QVW) in Some Backup Folder
than Delete the it.
After doing this, Simply Copy & Paste the Second Task (QVW) from Backup Folder to your Main Mounted Folder (Publish Folder) from where you have earlier deleted the Second Task (QVW)
Hope that helps you.
Regards
Av7eN
thank you Shiva for your response. I will check that and get back to you .
thank you Av7en for your response. let me see whats going on and i will get back to you . thanks a lot for your help.
hi Shiva, Where are you from. I have an opportunity. I can share with you. let me know if you are interested.
I'm frm AP/IND, not now,thanks.
Hi Av7en,
How can i make a back up of the task. Can you please guide me. I never did that.
Here I am referring task to your Stage-2 QVW.
ok let me see what i can do . i will get back to you with result.