Hi all,
We have a task which is running multiple times than the schedule time after upgrading to in qv 12.1 .
taskname : DDDD
we have defined like this:
Task DDDD should trigger once the completion of multiple dependant tasks AAAA,BBBB,CCCC.
taskname1: AAAA (exe time: 10 mins)
taskname2: BBBB((exe time: 8 mins)
taskname3: CCCC ((exe time: 15 mins)
task name DDDD sholud only trigger after completion of all taskname1,taskname2,taskname3.
we have scheduled task1,task2 task3 to run every 4 hours.
but now task DDDD is triggering before the completion of CCCC and completion of either AAAA or BBBB.
ex: suppose taskname1,taskname2,taskname3 schedules to run at 2 am UTC then taskname DDDD shold run after completion of above 3 tasks say around 2.35 am ,but its running at 2.11 and 2.16 and 2.19 and 2.20
so the taskname CCCC is failing to refresh the QVDs.
Its working fine in Qlikview 11.2 and we have updated to QV 12.1 and we are facing the issue .
need help in this
Just make the schedule chainning when finish CCCC start DDDD
So DDDD will always run after CCCC
There is a known potential issue in the QlikView 12.10 track where the Multiple Event trigger functionality may result in the task being triggered running more often than it did in the QlikView 11.20 and 12.00 tracks.
The issue will be addressed in a future release.
For more information refer Article Number:000028374