Skip to main content
Announcements
Customer Spotlight: Discover what’s possible with embedded analytics Oct. 16 at 10:00 AM ET: REGISTER NOW
cancel
Showing results for 
Search instead for 
Did you mean: 
deepti_singh
Creator II
Creator II

Reload a task stuck in QMC

Hi All,

There is a task (Task2) in QMC that is supposed to reload successfully "On Event from Another Task" (Task1). The Task1 is running successfully everyday. In the Tasks tab, theTask2 is showing status as "Running" since 10 days. This task takes 42min on an average to run, but neither the "Task History" nor the "Status" is being updated since 10 days. Also the "Started/Scheduled" must show "When ....Task1...", but is shows the 10days back date.

When I try to reload this task by opening the QlikView application and reloading it manually, its runs fine and the log shows no error.

Note- The "Automatic refresh of the task list" is checked. Also the Task2 is enabled.

Thanks.

Regards,

Deepti

1 Solution

Accepted Solutions
deepti_singh
Creator II
Creator II
Author

Stopping all the QlikView Services and starting them again fixed this error.

Thanks.

Regards,

Deepti

View solution in original post

2 Replies
deepti_singh
Creator II
Creator II
Author

Stopping all the QlikView Services and starting them again fixed this error.

Thanks.

Regards,

Deepti

qlikviewwizard
Master II
Master II

Hi deepti_singh,

Yes it is better to restart the QV services from the server. Good to hear