Hi Experts,

      In UAT 2*Processor with 128GB RAM and In Production 4*Processor with 256GB RAM even though if I run the same application these two machines UAT performance is better than the production server.but I noticed

In UAT Number of Cores it has 8,8 and Number of Logical Processors it has 16,16

In Production Number of Cores it has 8,8,8,8 and Number of Logical Processors it has 8,8,8,8 whether it could impact the performance?

I need some help.Advance Thanks.

Thanks & Regards,

Bala

1 Reply
Not applicable

Hi Bala,

This attachment will help you to understand the CPU utilization and its performance.