I am looking for 2 formulas, one for the load script and one for an expression in a chart. Both formulas calculate the difference in two dates and have the same outcome.
I want to subtract two dates to find the date difference, however I only want to include working days.
for example (24/11/2009 - 20/11/2009) = 4 days, I want the answer to read 2 days as the 21/11/2009 and the 22/11/2009 are saturday and sunday and should therefore the excluded from the equation.
many thanks!
Hi,
a hint is "NETWORKDAYS()". See QV help file.
Rainer
thanks guys!