We have projects allocated to each machine and one machine is having more than one projects allocated due to forecast….
Objective is to find out on which day which Machine is available/free to allocate future project…
Data : Something like below
Machine | Project | StartDate | FinishDate |
M1 | P1 | 09/06/2014 | 10/06/2014 |
M1 | P2 | 12/06/2014 | 12/06/2014 |
M2 | P3 | 08/06/2014 | 11/06/2014 |
M2 | P4 | 15/06/2014 | 16/06/2014 |
M2 | P5 | 20/06/2014 | 22/06/2014 |
M3 | P6 | 08/06/2014 | 12/06/2014 |
M3 | P7 | 18/06/2014 | 22/06/2014 |
M3 | P8 | 24/06/2014 | 24/06/2014 |
Output required:
ReportingDate | M1 | M2 | M3 |
08/06/2014 | YES | NO | NO |
09/06/2014 | NO | NO | NO |
10/06/2014 | NO | NO | NO |
11/06/2014 | YES | NO | NO |
12/06/2014 | NO | YES | NO |
13/06/2014 | YES | YES | YES |
14/06/2014 | YES | YES | YES |
15/06/2014 | YES | NO | YES |
16/06/2014 | YES | NO | YES |
17/06/2014 | YES | YES | YES |
18/06/2014 | YES | YES | NO |
19/06/2014 | YES | YES | NO |
20/06/2014 | YES | NO | NO |
21/06/2014 | YES | NO | NO |
22/06/2014 | YES | NO | NO |
23/06/2014 | YES | YES | YES |
24/06/2014 | YES | YES | NO |
HERE YES means, machine is available for project on that day and NO means, it's already in use....
May be something like the attached
You can intervalmatch reporting date to [StartDate, FinishDate]?
Cant' use as original Database is much more complex....
May be something like the attached
Excellent... I was an inch away ... 🙂