Do not input private or sensitive data. View Qlik Privacy & Cookie Policy.
Skip to main content

Announcements
Posting on Qlik Community is temporarily paused for some users. Thank you for patience and we'll update you soon!
cancel
Showing results for 
Search instead for 
Did you mean: 
yashcena
Contributor III
Contributor III

Change Font Color

Hi,

I have a chart where I'm projecting available hours of resources for the future.

It looks like this:

Capture.JPG

In the week of 09/30, the availability increases by 2 hours. So I want the text color to change to black.

When the availability changes again, I want the text color to change black to red.

I have written simple expressions for background and text color of the chart-expressions (shown below) but I'm not able to include the functionality of changing colors with changing availability.

Background:

=IF ($(vRemainingHours)<0,RGB(0,0,0),

IF(($(vRemainingHours)>=1 and $(vRemainingHours)<=6) ,RGB(177,106,103),

IF(($(vRemainingHours)>=6.1 and $(vRemainingHours)<=13),RGB(244,156,89),

IF(($(vRemainingHours)>=13.1 and $(vRemainingHours)<=20),RGB(255,217,99 ),

IF(($(vRemainingHours)>=20.1 and $(vRemainingHours)<=27),RGB(206,247,129),

IF(($(vRemainingHours)>=27.1 and $(vRemainingHours)<=35),RGB(79,170,115),

IF(($(vRemainingHours)>=35.1 and $(vRemainingHours)<=42),RGB(179,224,245),

IF(($(vRemainingHours)>=42.1 and $(vRemainingHours)<=49),RGB(154,155,156),

IF($(vRemainingHours)>=49.1 ,RGB(0,0,0)

)))))))))

Text:

=IF ($(vRemainingHours)<0,RGB(255,0,0),

IF(($(vRemainingHours)>=1 and $(vRemainingHours)<=6) ,RGB(255,255,255),

IF(($(vRemainingHours)>=6.1 and $(vRemainingHours)<=13),RGB(0,0,0),

IF(($(vRemainingHours)>=13.1 and $(vRemainingHours)<=20),RGB(0,0,0),

IF(($(vRemainingHours)>=20.1 and $(vRemainingHours)<=27),RGB(0,0,0),

IF(($(vRemainingHours)>=27.1 and $(vRemainingHours)<=35),RGB(255,255,255),

IF(($(vRemainingHours)>=35.1 and $(vRemainingHours)<=42),RGB(0,0,0),

IF(($(vRemainingHours)>=42.1 and $(vRemainingHours)<=49),RGB(255,255,255),

IF($(vRemainingHours)>=49.1 ,RGB(255,255,255))))))))))

$(vRemainingHours) is my chart-expression.


The condition to change the text color should be added in the text color-expression.


Also, is there any other/better way to depict availability change in the above chart so that it's more visually attention-catching?


Any help would be appreciated!


Thanks,

YASH

Labels (1)
0 Replies