EXPRESSION

This expression is not working

SUM({<POL_PERIOD_TO<={'31-08-2014'}>}PREMIUM)

Pls tell me how to correct it

Thanks

Labels (1)
1 Solution

Accepted Solutions
upaliwije
Creator II
Creator II
Author

ThankS

It is working

View solution in original post

5 Replies
tresB
Champion III
Champion III

Right syntax is:

SUM({<POL_PERIOD_TO={'<=31-08-2014'}>}PREMIUM)

perumal_41
Partner - Specialist II
Partner - Specialist II

Hi

please upload sample application.


upaliwije
Creator II
Creator II
Author

ThankS

It is working

Not applicable

Hi please close the thread

senpradip007
Specialist III
Specialist III

I think Tresesco has given the right answer. Hence his post should be marked as Correct Answer instead of others...