Hello,
I'm working on creating a basic gantt chart, which I've succeeded on thanks to these forums.
The horizontal bar is broken down by %complete in red and %remaining in green.
The yellow line is added in with paint and what I'm trying to get QlikView to do. I'd like to create a vertical line for todays date.
The closest I could come is putting in another expression for todays date and making it an average trend line which comes out close, if it were possible to suppress the horizontal portions.
Any suggestions on how to get the desired effect?
Thanks,
-Ken
Have you tried a Reference Line with the expression =today()?
-Rob
I have not, and that will solve my problem perfectly. Thanks!
Still pretty new to QlikView and working my way through all of the options.
Glad it worked for you. Thanks for marking the answer verified and welcome to Qlikview.