Help!! Show early/late progress on chart

Dear all,

This is something I've been tackling with for a week or two now, and could do with some guidance. I have created a gantt chart using bar offset and another using invisible bars. Please find my workings attached. Show the chart itself doesnt seem to be an issue, however, I would also like to show where I started/finished early with a green blob, and where I started/finished late with a red one... I nearly did it with invisible bars, but not sure how to start with bar offset!

Could you have a look and assist me with my query?

Many thanks!
Dayna

Labels (1)
3 Replies
Dayna
Creator II
Creator II
Author

Anyone? 😞
rwunderlich
Partner Ambassador/MVP
Partner Ambassador/MVP

It looks just fine to me on QV9 SR4.

Dayna
Creator II
Creator II
Author

Hello Rob,

Unfortunately it's not, if you look carefully at the early starts, they don't correlate with the data....