Need Suggestion

Hi Friends,

I have below data with start dates available, i need to derive end date for users by looking at start date of project change. In below data, i have put end date manually which needs to be derived. Please suggest

   

UserIDUserNameProjectStart DateEnd Date
100User1Project101-02-201601-04-2016
101User2Project101-02-2016
102User3Project101-02-201601-08-2016
103User4Project101-02-2016
100User1Project201-04-201601-07-2016
100User1Project101-07-201613-12-2016
102User3Project301-08-2016
Labels (1)
6 Replies
shraddha_g
Partner - Master III
Partner - Master III

What is the logic for End date?

marcus_sommer
MVP
MVP

Within a to UserID and Project sorted load you could query and evalaute the values from the previous record per Peek() or Previous() ?‌ and evaluate your needed result appropriate.

- Marcus

Anonymous
Not applicable

Do these projects have different durations? You can estimate a time duration and try to automate the completion of the end date.

manojkulkarni
Partner - Specialist II
Partner - Specialist II
Author

Next available start date for User

manojkulkarni
Partner - Specialist II
Partner - Specialist II
Author

There is no exact duration specified. It is only noticed when user change to next project

sasikanth
Master
Master

HI Manoj,

try this Script below

TEMP:

Load * Inline [

UserID ,UserName ,Project, StartDate

100, User1, Project1, 42371

101, User2, Project1, 42371

102, User3 ,Project1, 42371

103, User4, Project1, 42371

100, User1, Project3, 42376

100 ,  User1 ,Project2, 42373

102 ,User3 ,Project3, 42377

];

TEST:

LOAD * ,IF(UserID=Previous(UserID) and UserName=Previous(UserName)and Project<>Previous(Project) ,previous(StartDate)) as EndDate

resident TEMP ORDER BY UserID,UserName,Project desc ;

DROP Table TEMP;