Hi

I have 3 Tasks

A

B

C

I want to schedule task B to run once Task A is successfully complete and also Task B should run every 3 hrs  once...Can I do this ?

Labels (1)
1 Reply
Anil_Babu_Samineni
MVP
MVP

If you have Publisher then you may need to do Dependency

"WHEN Task A is successfully Done"

Then create,another reload for Task B which called 3 hours from Reload Tab of our local Server.