Looking for an option to change the order of tasks in a plan step, see attached.
But it looks like the tasks are added in alphabetical order only???
Example:
In the step Paymentech_US, I would like the checkfileName task to run first then the AllPaymentech_UCR task to be next?
I know if I change the names of the task I could probally get it to work, but wanted to see if I was missing something else.
Thanks for any help.
Hello @Robert Veitch ,
Yes, the tasks are added in alphabetical order only in a step.
For your case, you can create 2 steps in a plan, the 1st step with checkfileName task, the 2nd step with AllPaymentech_UCR task
Best regards