Plot S-Curve Line Chart with Only Start & End Values

Hi, I hope someone out there can please help me with this.

I have a data set that has fixed date increments for each project and a start & end value. I'm trying to plot a S Curve line chart when a specific project is selected (as the sample picture below) with the dates as dimension and I need to calculate the values between the start and end values. Any ideas to calculate this either in the script or the chart would be greatly appreciated, thanks

SimonDB_0-1643151107876.png

My Data looks something like this:

LOAD * INLINE [
Project Row Number, Project Name, Quarter Date, Start Value, End Value
1, TEST1, 01/01/2026, 150,000, 10,000,000
2, TEST1, 01/04/2026, 150,000, 10,000,000
3, TEST1, 01/07/2026, 150,000, 10,000,000
4, TEST1, 01/10/2026, 150,000, 10,000,000
5, TEST1, 01/01/2027, 150,000, 10,000,000
6, TEST1, 01/04/2027, 150,000, 10,000,000
7, TEST1, 01/07/2027, 150,000, 10,000,000
8, TEST1, 01/10/2027, 150,000, 10,000,000
9, TEST1, 01/01/2028, 150,000, 10,000,000
10, TEST1, 01/04/2028, 150,000, 10,000,000
1, TEST 2, 01/01/2022, 0, 2,500,000
2, TEST 2, 01/04/2022, 0, 2,500,000
3, TEST 2, 01/07/2022, 0, 2,500,000
4, TEST 2, 01/10/2022, 0, 2,500,000
5, TEST 2, 01/01/2023, 0, 2,500,000
6, TEST 2, 01/04/2023, 0, 2,500,000
1, 3 TEST, 01/01/2023, 800, 12,000
2, 3 TEST, 01/04/2023, 800, 12,000
3, 3 TEST, 01/07/2023, 800, 12,000
4, 3 TEST, 01/10/2023, 800, 12,000
5, 3 TEST, 01/01/2024, 800, 12,000
6, 3 TEST, 01/04/2024, 800, 12,000
7, 3 TEST, 01/07/2024, 800, 12,000
8, 3 TEST, 01/10/2024, 800, 12,000
];

 

Labels (2)
1 Solution

Accepted Solutions
SimonDB
Contributor III
Contributor III
Author

3 Replies
Qrishna
Master
Master

Hi - 

1. Make a list box with 'Project Name,' field
2. Create a Line Chart with 'Quarter Date' as dimension
3. measure = [End Value] - [Start Value]

As your [End Value] , [Start Value] are constant  across any given TEST, you see a straight line rather than a curve.

 

Capture.JPG

 

SimonDB
Contributor III
Contributor III
Author

Hi, this wouldn't work for me. The Start Value sits with the first date and the end value sits with the last date. I need to calculate the values as a S Curve for the dates between the start and end. I believe this can be done using STDEV and/or NORMDIST, but I've no idea how to plot the expression 

SimonDB
Contributor III
Contributor III
Author