Hi,

 I am trying to create of chain of subjobs with loops as you can see on picture 0683p000009LrCH.png

but the  second loop is not started.

 

I want to run it in sequence after finishing while condition in the first loop.

r.

 

 

Labels (2)
1 Solution

Accepted Solutions
Anonymous
Not applicable

Hi there,

 

Whilst it's not possible to know the logic you're using just from a screen grab of your job, I suspect that the condition used in the second tLoop simply is evaluating to false at the point the sub-job is started, and so there are no iterations.

 

Regards,

 

 

Chris

View solution in original post

2 Replies
Anonymous
Not applicable

Hi there,

 

Whilst it's not possible to know the logic you're using just from a screen grab of your job, I suspect that the condition used in the second tLoop simply is evaluating to false at the point the sub-job is started, and so there are no iterations.

 

Regards,

 

 

Chris

Romanesku
Contributor III
Contributor III
Author

Thx, you are right, missed setting and is evaluating to false.

 