Dear all.
I am using in Qliksense some doughnut charts and would like the total value to be displayed in the middle of the graph. Any way I can do this?
Thank you for your help.
Joerg
I don't think there is a way to do it using the default settings.
Maybe it's easier to put a simple KPI under the chart with total.
you can't show in Middle of Doughnut but can show in chart TITLE
keep the expression in chart title
Hell @Joerg_Linder
You can support this idea : https://community.qlik.com/t5/Ideas/Doughnut-with-internal-total-KPI/idi-p/1614215
Best regards,
Simon
@Joerg_Linder , It can be possible if you specify the limitation of fixed number to 1 for Top or bottom or else you can specify expression as per requirement . Check the same as attached.