Unlock a world of possibilities! Login now and discover the exclusive benefits awaiting you.
Good Morning,
as stated in subject, I have some daily reload processes that were scheduled during last months. On last weekend, here has started the Daylight Saving Time period and all scheduled processes are now starting one hour later than before.
The strange thing is that, opening schedule properties form, the time of schedule is correct but planning isn't.
Let's see an example. Considering the highlighted process:
If you open its properties form, it has one daily trigger schedule. Double click on it:
Even if you try to change start time and save, schedule shift remains. E.g.: if you set the above one to 10:15, after saving it you see this:
The only way you have is to delete and re-create the trigger.
Ciao.
Paolo.
This has been sort of answered, but yes, it is a bug (one of them was logged by me) which has not been fixed but do let us in Support know so that we can report another customer experiencing / having issues with it to properly prioritize it with R&D.
Glad to see that it has been fixed in 3.0.1
Regards,
Paolo.
My tasks were running an hour ahead of schedule.
I resolved by changing from "Observe daylight saving time" to "Permanent standard time" in the "Daylight saving time" option for each task that had time scheduling.
Hope this helps
Qlik Sense June 2017