Fabien_S
Partner - Contributor II
Partner - Contributor II

Can't run multiple Nprinting tasks in parallel

Hello there,

I'm currently using Nprinting May 2021 SR2 (21.14.5.0), I have 2 CPU and 2 virtual cores.

My problem is that all my Nprinting task runs one after the other and not simultaneously. Do you guys have any idea about what could be the reasons it doesn't work ?

Thanks in advance,

Fabien.

Labels (1)
6 Replies
Lucas_Gatling
Support
Support

Fabien,

How much RAM does each of your CPU Cores have? See the minimum requirements: https://help.qlik.com/en-US/nprinting/May2021/Content/NPrinting/DeployingQVNprinting/System-requirem...

If the issue is solved please mark the answer with Accept as Solution.
Ray_Strother
Support
Support

Hello ,

1. How are the resource utilization during the report generation?
2. Review the following link which describes the Nprinting resource utilization.
3. Review the links below for Nprinting connections to Qlik products.

Article links:

1. https://community.qlik.com/t5/Official-Support-Articles/How-NPrinting-consumes-resources-when-connec...

2. https://help.qlik.com/en-US/nprinting/May2022/Content/NPrinting/GettingStarted/HowCreateConnections/...


3. https://help.qlik.com/en-US/nprinting/May2022/Content/NPrinting/GettingStarted/HowCreateConnections/...
Fabien_S
Partner - Contributor II
Partner - Contributor II
Author

Hello Lucas,

I have 8Go of RAM in total, I'm pretty sure I have all the requirements to run tasks simultaneously.

Do I have to change any settings in Admin or anywhere else to specify precisely to Nprinting that I want to run tasks in parallel ?

Frank_S
Support
Support

If you run say 20 publish tasks and you only have 2 cores/processes, Nprinting scheduler and engine will assign jobs to 2 available processes.

To improve your situation to run more reports/tasks executions simultaneously, you would need to add more CPU's/hyperthreaded processes.

AT the moment in your environment, some of your tasks will have to wait until some cpu processes become available. Adding resources (CPU and RAM) is probably a good idea.

You can use this hidden link to view the NP scheduler/engine at work as well. Replace your NPserver name with your own.

https://mynpserver:4993/#/admin/plan

For more information about performance, visit: https://help.qlik.com/en-US/nprinting/May2021/Content/NPrinting/DeployingQVNprinting/Performance.htm

For more information about sizing your environment see: https://community.qlik.com/t5/Official-Support-Articles/Finetuning-and-preparing-your-NPrinting-19-D...

Kind regards...

Please remember hit the 'Like' button and for helpful answers and resolutions, click on the 'Accept As Solution' button. Cheers!
Fabien_S
Partner - Contributor II
Partner - Contributor II
Author

Thanks for you answer Lucas,

The real problem is that even with my 2 CPU, 2 virtual cores and 8Go RAM, i can't even run 2 tasks at the same time.

There must be something that makes it impossible right ?

Kind regards.

David_Friend
Support
Support

@Fabien_S I agree with Frank, 2 CPU and only 8GB of RAM is a very very minimal configuration, I would first bump up both of those and then watch for any changes in performance...if after adding CPU/RAM performance still seems low, suggest opening a support case.