Hello all,
This has happened several times and we couldn't find out what's wrong.
We have set up task on QV server to run files every morning. They are triggered one by one.
Then what happened is the log file shows the QV file has been reloaded successfully for example for today but the QV file still shows the date for yesterday and the data is like not reloaded.
Anyone know anything about it?
Thanks.
Fei
Thank you guys. We have found out the reason is that the hard disk is running out of space. So when the first task finishes reloading, it cannot save and overwrite the QV file but it can kick off the next task. The result is every task looks reloaded successfully in log file but the QV files are not updated.
Fei,
Does the task in the QMC show that it's still running?
Vlad
It would be helpful if you would give the version of QlikView that you are having issues with. That way we can check to see if there is a possible bug causing your issue.
Bill
Thank you guys. We have found out the reason is that the hard disk is running out of space. So when the first task finishes reloading, it cannot save and overwrite the QV file but it can kick off the next task. The result is every task looks reloaded successfully in log file but the QV files are not updated.