Hi,

I had 5 tasks namely task1,task2,task3,task4 and task 5.

First I will run task1 and after completion of task, remaining tasks need to start

I added task2,task3,task4,task5 as dependencies under task1.

But, Remaining tasks are not triggered after successful completion of task1..

Please provide solution and need some sample images how i can add multiple triggers for one task..

Thanks

Nagaraju

2 Replies
Not applicable

Hi,

You need set the other task to start on completion of the first task.

If I understand you correct, you like task 1 to run , then all other should run when task 1 is done?

So if task1 has run and is a success, the other tasks should start

tasktrigger.JPG.jpg

Not applicable

Sorry about posting wrong screen, you should use "On multiple events completed" it´s in the same configuration screen as posted.