Hi All,
We are currently using publisher 8.5. We have multiple documents which are reloaded in parallel in publisher. Is there a way by which we can create dependencies on these documents which run in parallel .
Thanks,
Haneesh
If document runs in parallel then what is the need of dependency ?
If you want to trigger your task one after the other then you have EDX option(I am not familiar with) in 8.5 however in 9.0 we have option to trigger a task after successful/failed execution of another task.
Hi,
We need to run several two document sets in parallel with a dependency on the whole lot. For example, we must run A before B, C before D; A/B and C/D can be run in parallel and E must wait until both are complete before executing.
How can I start the reload of E when A/B and C/D load completes.
Regards,
Haneesh
any comments on this?
Things which you are looking for is available in version 10 that a task 3 starts when task1 & task2 gets completed.
Till 9.0 SR5 you can schedule task3 only after task1 completion or after task2 completion.
Can't be dependent on both.