I'm looking for formula in edit expression where I could get automatic update of current 4 weeks once new week becomes available.
I know how to create date ranges that are not dynamic, I'm looking for dynamic update.
i.e if I have weeks 1/18/13' & 1/25/13' & 2/1/13' & 2/8/13' = Current 4, I need automatic calculation to update my Current 4 Week
calculation once week 2/15/13' becomes available.
try this:
sum({<weekdate={">=$(=date(max(weekdate)-21)) <=$(=date(max(weekdate)))"}>}data).
Also find attached sample app
Your attached file doesn't seem to have any data in it
are u using personal edition?
Yes
Please find the attached..
HTH
Sushil
I can see it now, but I think I'm looking for something else. If you had one more dimension such as Region, and you wanted to see C4 (Current 4 weeks) of data, vs. P4 (Previous 4 weeks) by Region
I really don't want to see dates, just two "buckets" of C4 & P4 by Region i.e below
Region C4 P4
Region A 15 20
Region B 17 25
Thanks
Can u provide the sample data?
I've got my answer through my boss - "Thank You boss!"
Thanks for your help. Here is what I got for current. If you want to go with previous you'd need to subctract instead of 21, 49 than 28 after [Week Ending Date]
Best,
Rafa
sum
({$<[Week Ending Date]={'>=$(=date(max([Week Ending Date])-21,"MM/DD/YYYY"))<=$(=date(max([Week Ending Date]),"MM/DD/YYYY"))'},[Product]={'TWA1'},
[Type]={'RETA'},[Payer]={'ABC'}>}Sales)