I have to calculate the amount of hours that a request takes to move through our system. I have several Date/Time fields to use in my calculation (formatted as YYYY-MM-DD HH:MM:SS). These are the fields I am using:

Origination Date/Time

HR Approval Date/Time 1

HR Approval Date/Time 2

HR Approval Date/Time 3

HR Approval Date/Time 4

I need the difference between the last HR Approval we have received and the Origination Date/Time. I know it's the difference between the Approval and Origination fields, but I'm not sure how to take into account that it can be any of the 4 approval fields. I hope this makes sense!

Thanks,

Jennifer

1 Reply
rwunderlich
Partner Ambassador/MVP
Partner Ambassador/MVP

How about:

RangeMax([HR Approval Date/Time 1],
[HR Approval Date/Time 2],
[HR Approval Date/Time 3],
[HR Approval Date/Time 4]) - [Origination Date/Time]