Hello,
I need some help. I need a do while loop like this:
a, b, c and d are all fields out of tables and all are Dates. I'm a beginner with QlikView, so I hope it will be not so difficult.
I tried it, but it do not work.
Thanks for all help!!
do while (a=b)
load
rangesum ((b-a),c) as LD,
NetWorkDays (d, rangesum((b-a),c)) as AT
Resident Temp2;
Let a=At; c=LD;
loop
Result:
load *, delivery_date - goods_issue_date as delivery_time;
load goods_issue_date, no_of_working_days,
lastworkdate(goods_issue_date, no_of_working_days) as delivery_date
from ...etc
Hi
Your code does not make any sense to me, you appear to be using a, b, c as variables in some places and as fields in others.
Can I suggest that you explain what you are trying to achieve and I expect that someone will then be able to help you.
Regards
Jonathan
Ok, I try.
Also, I have 4 dates in a table, this are the delivery time in days, the delivery date, the goods issue date and the workingday between the delivery date and the goods issue date.
I have the Problem, that I have to calculate the delivery date by my self out of the delivery time and the goods issue date. So it can be, that the delivery date will be on a Saturday or Sunday, but this is not true.
So I help me with the workingdays between the delivery date and the goods issue date.
The delivery time must be the same as the working days between the goods issue date and the delivery date.
Now you can replace a,b,c and d with this four dates.
a should be the working days between the goods issue date and the delivery date, b the delivery time, c the delivery date and d the goods issue date.
In the end I will have a right delivery date, which is not on saturday, or sunday.
Maybe its a lot easier than I tried it.
I hope you understand me and can help me now. If anything is unclear, please ask for it, I try to explain.
Thank you very much für your help!!
Result:
load *, delivery_date - goods_issue_date as delivery_time;
load goods_issue_date, no_of_working_days,
lastworkdate(goods_issue_date, no_of_working_days) as delivery_date
from ...etc
Hey,
thanks very much. It works, but it don't include my holidays.
tmpFeiertage:
LOAD Date([Feiertagsdatum]) as Date
FROM .\qvd\Betriebskalenderfeiertage.qvd (qvd);
tmpVerkettung:
LOAD concat(chr(39) & tmpFeiertage.Date & chr(39),',') AS Feiertagsdatum
RESIDENT tmpFeiertage;
Let vFeiertage = fieldvalue('Feiertagsdatum',1);
DROP TABLE tmpFeiertage;
DROP TABLE tmpVerkettung;
Temp2:
Load *,
LastWorkDate (date([Temp.Warenausg_-Datum]), Temp.TransportTage, $(vFeiertage)) as Lieferdatum
resident Temp;
Is this right? It don't note the holidays.
Regards
Alex
Hi
I think you need to change tmpVerkettung as follows:
tmpVerkettung:
LOAD chr(39) & concat(chr(39) & tmpFeiertage.Date & chr(39),',') & chr(39) AS Feiertagsdatum
RESIDENT tmpFeiertage;
And I would use peek rather than FieldValue:
Let vFeiertage = Peek('Feiertagsdatum');
The rest of the script looks correct to me.
Regards
Jonathan
Hey.
thanks a lot. I think now it works correctly.
Regards
Alex