I am trying to produce a Gant chart that shows activity over a day. The table of data is similar to the below:
Task | Job | Start Time | Duration |
---|---|---|---|
A | 1 | 09:00 | 00:15 |
A | 9 | 17:00 | 00:15 |
C | 4 | 12:00 | 00:20 |
C | 8 | 16:00 | 00:20 |
A | 2 | 10:00 | 00:20 |
B | 3 | 11.00 | 00:15 |
B | 7 | 13:00 | 00:15 |
A | 7 | 15:00 | 00:15 |
B | 6 | 14:00 | 00:20 |
My desired outcome would look similar to the below - where "non captured" time is simply a gap between tasks
Can anyone give me some guidance on how to do it? Please note that my data is not ordered.
I've tried previously to create a bar chart with the Jobs plotting across the bottom and using a bar offset to plot the duration amounts in the correct place but I don't think it is possible to overlap the separate jobs so it is only in one column?
Any advice/help would be greatly appreciated.
Many thanks.
Drew
It seems you need to adjust the scale
Try stacked chart
Here you are an example of Gannt
Hi Enrique,
This is useful but I would now need to plot all of the "promocion"s on one column - the reason I that my data might have 300 "promocion" options.
Thanks,
Drew
OK, you can modify input data with gaps in colour=blank
Hi Enrique,
This is useful but your jobs are still not showing on one column? The issue is that in my data I may have Jobs up to number 200 so this wouldn't visually work with this amount of data. Thank you for your help though.
Drew
Does anyone else have any thoughts on this? I need to have the information plotted on the same bar (in excel you can use series overlap)
Hi,
You could try this approach:
How to create a Gantt chart using a Pivot table
It's different because it uses colored cells in a pivot table instead of using a bar chart. Still it may be helpful.