Hey!
Let say i have a worked hours, and payed hours in execel as two collums. Lets also say i have a date collum with the date, for example, 2011-01-31, lets also say that i have a collum month.
Worked hour Payed hours Date Month
4 4 2011-01-02 Jan
5 3 2011-03-31 Mars
6 6 2011-01-31 Jan
7 5 2011-02-24 Feb
Now i want to plot this, and thats no problem, i use the Moth as dimention. And use tree functions, sum(Worked hour), sum(Payed hours).
Then I make a list with the dates and month so i can choose between them.
My problem is how to sort the x-axis of the diagram and the month list. I want ofc Jan,Feb,Mars. But i get Jan, Mars, Feb.
Quite hard to explain but I hope someone understans. (I use the loadorder from execel)
You can put a 1 column table at the beginning of the script with the Months in your preferred order and then use the "Load Order" sort option.
LOAD * INLINE [
Month
Jan
Feb
Mar
...
];
You can put a 1 column table at the beginning of the script with the Months in your preferred order and then use the "Load Order" sort option.
LOAD * INLINE [
Month
Jan
Feb
Mar
...
];
Sweet, so the load order takes the first one, sweet. Now it works!
Hi,
Go to the chart properties -> Sort
Select expression in the sort order and write the following code there:
=Match(Month, $(=chr(39) & Replace(MonthNames, ';', chr(39) & ',' & chr(39)) & chr(39)))
This will sort your month in the proper order
Thanks
Manisha Choudhary
Hi Johan,
Thanks for the tip about sorting months. After creating INLINE, what's next?
Thanks.
Don