Reload Task

Hi

I have schaduled a task to run everyday, however it will only start running on 01/01/2015.

I would like it to start running from tomorrow onwards. Where can I change this setting?

2014-12-13_13-12-11.png

1 Solution

Accepted Solutions
8 Replies
advait_thakur
Creator III
Creator III

Hello Stewart,

To perform such activity, you need to visit in QMC > Documents > Source Documents and edit task after which you need to visit Trigger tab.You may Trigger the application task by keeping tomorrow's date.

Regards

Advait

Join the official Qlik Enthusiast's page here
https://www.linkedin.com/groups/6513382/
Not applicable
Author

Hi Advait

I do not see the Trigger tab in QMC

2014-12-13_14-28-01.png

Or are you refering to the one on the document properties?

arulsettu
Master III
Master III

hi

in the above image there is start column why dont you change there?

Not applicable
Author

Hi

That start column only applies for hourly reloads. when I change it to daily, it ges back to 01/01/2015.

arulsettu
Master III
Master III

Server Settings

Change Preloaded to Restricted and select a Days what you want!

Not applicable
Author

Hi

I tried that, it doesn't help.

arulsettu
Master III
Master III

advait_thakur
Creator III
Creator III

Hi,

Apologies, I assumed you are having QlikView Publisher.

In this case you need to check the option Enable, please refer to the link which Arul has posted.

Regards

Advait