Hello community,

I have projects that have start (SOP) and end dates (EOP) - in a bar chart how can I write the Label Expression so that each project is shown with it's own start and end date when hovering over it?

At the moment I have: =Min(Date(SOP)) &' - ' & Max(Date(EOP))  which doesn't lookup the dates for each individual project but shows the overall min and max dates.

I can't get the set analysis right.

Thank you.

1 Solution

Accepted Solutions
MK_QSL
MVP
MVP

9 Replies
MK_QSL
MVP
MVP

Please check enclosed file.This will give you idea...

Not applicable
Author

thanks for the sample Manish.

Almost perfect. How can I get rid of the =29.11.1904 which I believe comes from the Definition of the Expression: =Max(Date(EOP))-Min(Date(SOP)) - I put a blank in the Label but it didn't work.

project.PNG.png

I have everything unchecked in the Display Options (Besides 'Bar')

MK_QSL
MVP
MVP

Like This ?

MK_QSL
MVP
MVP

Have you tried as per my 2nd reply?

Not applicable
Author

Hello Manish,

sorry for the delay.

I should add that I've built a gantt-chart using the "Bar-Offset" property but I don't see why this shouldn't work.

I copied your expression and changed the Sum(Sales) back to "=Max(Date(EOP))-Min(Date(SOP))"

but without luck.

Attached you'll find a little sample with what I have.

MK_QSL
MVP
MVP

In expression

For Label >> untick values on data points

For INFO >> Tick Values of data points

Not applicable
Author

but now I have the dates as a label instead of the project but I need it the other way around -> project name right of the bar and then both dates when hovering over one bar.

MK_QSL
MVP
MVP

Enclosed.

Not applicable
Author

Perfect! Thank you very much.