This may be a very stupid question, but can somebody tell me how i use the 'Number interpretation variables'.

On load i am setting a system variable call 'LongMonthNames'. If i have a date '02/06/2012' how can i use 'LongMonthNames' to return June.

I have attached a file with Months 1 to 12 so you can see what i mean.

LongMonthNames='January;February;March;April;May;June;July;August;September;October;November;December';

Cheers

Robbie

1 Solution

Accepted Solutions
Not applicable
Author

Robbie,

All the functions seem to use the format as defiend in MonthNames eg if you change your script to:

load Month,

month(Month) as monthname;

LOAD * INLINE [

    Month

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

];

It will return 'Jan' 'Feb' etc. The LongMonthNames only seems to have a value when formatting a date (MMM returns eg 'Jan' whereas 'MMMM' returns 'January'.

Easiest way I know is to just change the definition of MonthNames:

SET MonthNames='January;February;March;April;May;June;July;August;September;October;November;December';

Regards,

Gordon

View solution in original post

3 Replies
Not applicable
Author

Robbie,

All the functions seem to use the format as defiend in MonthNames eg if you change your script to:

load Month,

month(Month) as monthname;

LOAD * INLINE [

    Month

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

];

It will return 'Jan' 'Feb' etc. The LongMonthNames only seems to have a value when formatting a date (MMM returns eg 'Jan' whereas 'MMMM' returns 'January'.

Easiest way I know is to just change the definition of MonthNames:

SET MonthNames='January;February;March;April;May;June;July;August;September;October;November;December';

Regards,

Gordon

stephencredmond
Partner - Specialist II
Partner - Specialist II

Hi Robbie,

The values will be used in the Date format function when you use MMMM:

Load Dual(Text(Date(MakeDate(2012, Month), 'MMMM')), Month) As Month;

LOAD * INLINE [

    Month

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

];

Regards,

Stephen

Anonymous
Not applicable
Author