Hi Community,

Week numbers are often  used in calendar, we can create simple way WEEK(DATE) i.e 52/53 weeks.


I'm facing issue with Week level data, my users wants to show like below

Week 1
Week 2
Week 3
Week 4
Jan Week 5
Feb Week 5
Week 6
Week 7
Week 8
Feb Week 9
Mar Week 9

Week 1 to Week 4 under Jan month, but Week 5 is both in Jan and Feb... so it is not taking correct value.

I want Bifurcate 2 levels, like Jan Week 5 and Feb Week 5  and so on...


Any possibility??


Experts please suggest any better way....


Thanks in Advance!!

3 Replies
eduardo_dimperio
Specialist II
Specialist II

Is mandatory that your filter uses weeks?

Anil_Babu_Samineni

Not sure about your user needed. As i ma user, This is not make sense to me. If you select week 5 then what data will come up to the picture.

Best Anil, When applicable please mark the correct/appropriate replies as "solution" (you can mark up to 3 "solutions". Please LIKE threads if the provided solution is helpful
ogautier62
Specialist II
Specialist II

Hi,

use as dimension :

Month() + week()

regards