Do not input private or sensitive data. View Qlik Privacy & Cookie Policy.
Skip to main content

Announcements
Save an extra $150 Dec 1–7 with code CYBERWEEK - stackable with early bird savings: Register
cancel
Showing results for 
Search instead for 
Did you mean: 
yoganantha321
Creator II
Creator II

Weekends in separate color in Gantt Chart

Hi all,

I have a gantt chart with different colors based on the type. But i need to show the weekends (i.e saturday and sunday) as black color for all employees in all months.

Also, my x- axis is in month wise but i need as date wise. Any body help in this!!!

I have attached my sample file along with this.

Regards,

Yoganantha Prakash   G P

 

Labels (1)
1 Solution

Accepted Solutions
uacg0009
Partner - Specialist
Partner - Specialist

Hi Yoganantha,

Firstly I want to say that your qvw is really cool, I learnt a lot from your qvw. And I changed a little in your expression.

Hope below result is what you want.

Weekends in separate color in Gantt Chart.PNG

And about the date wise, I think actually your dimension is "Date", so it's date wise.

But maybe because the chart is not long enough, so qlikview will show part of date automatically.

You can see my sample, I change the width to 3000+, it shows 5 days step.

Thanks.

Aiolos

View solution in original post

4 Replies
uacg0009
Partner - Specialist
Partner - Specialist

Hi Yoganantha,

Firstly I want to say that your qvw is really cool, I learnt a lot from your qvw. And I changed a little in your expression.

Hope below result is what you want.

Weekends in separate color in Gantt Chart.PNG

And about the date wise, I think actually your dimension is "Date", so it's date wise.

But maybe because the chart is not long enough, so qlikview will show part of date automatically.

You can see my sample, I change the width to 3000+, it shows 5 days step.

Thanks.

Aiolos

yoganantha321
Creator II
Creator II
Author

Hi Alios,

Thanks for the comments and given the expected output.

 

Regards,

Yoganantha Prakash G P

uacg0009
Partner - Specialist
Partner - Specialist

You're welcome. Glad to help you~

Aiolos Zhao

tsegahun
Partner - Contributor
Partner - Contributor

Hi Yoganantha,

Did you get your solution to work? I've a similar requirement for a gantt chart but struggling to make it work. Your attached qvf doesn't have the visuals, only the script. Would you be able to share?

 

Thanks a bunch!

Tsega