Work Week

Is there any way to exclude all Saturday's and Sunday's from my date to make it a Monday-Friday work week?

I have two date fields and I want to calculate the difference between them as a plus or minus working days

Planned Date - Actual Date AS Working Days

At the moment it works fine but will sum all days when I want just Monday-Friday to be calculated

Labels (1)
10 Replies
khaycock
Creator
Creator
Author

This works perfectly, thank you so much for all your help 🙂