Hi Team,

I have 4 charts which is always minimized. When i restore one chart, it takes some time. In the Mean time, i need to show the users, some process is running like the attached gif. can you help on this?

3 Replies
phaneendra_kunc
Partner - Specialist III
Partner - Specialist III

Usually each chart will show some progress bar "GREEN" one if it takes little longer.

But adding GIF is not possible at this time i believe. or i didn't came across a way to do that.

settu_periasamy
Master III
Master III
Author

Hi,

When we restore one chart, it takes 10 seconds to appear. But we dont know, if it is clicked or not.

That's why i need to show to progress bar or some thing else. The user should aware some thing happening.

Any Suggestion ?

Thanks.

Sethu

ashfaq_haseeb
Champion III
Champion III

Hi,

Check if this helps